The Herald

Stage 2 load-shedding to be implemented on Sunday afternoon

Stage 2 load-shedding will be implemented from 4pm on Sunday.

Fleet Street police officers were left in the dark for almost two weeks.
Fleet Street police officers were left in the dark for almost two weeks. Fleet Street police officers were left in the dark for almost two weeks. Picture: 123RF/ beercrafter

Stage 2 load-shedding will be implemented from 4pm on Sunday.

Eskom announced at about 3.30pm that the load-shedding was “due to additional generation unit losses and delayed return to service of generators” and “only as a last resort to protect the national grid”.

“The loss of four additional generation units at Matla, Tutuka, Duvha and Arnot power stations over the past 24 hours, exacerbated by the delay in units returning to service at Camden, Matla, Grootvlei and Tutuka power stations, has unfortunately necessitated the implementation of load-shedding,” Eskom said. 

“The power system continues to be fragile and Eskom is forced to implement load-shedding to manage and replenish emergency generation reserves, on which it has been relying to supply electricity this week.

“Since Friday afternoon, a generation unit each at Camden, Komati and Arnot power stations returned to service.”

Eskom said they had 5,474MW on planned maintenance, while another 17,018MW of capacity was unavailable due to unplanned breakdowns.

“The power system remains unpredictable, and Eskom would like to inform the public that any further deterioration in generation capacity may require higher stages of load-shedding,” Eskom said.

“We therefore request the public to continue using electricity sparingly, as we strive to return units to service.”

The load-shedding is expected to continue until Wednesday.

Here are your Nelson Mandela Bay load-shedding schedules:

HeraldLIVE